The Rs 465 crore project includes identifying, procurement and development of required land, design, engineering, manufacture, inspection at supplier works, packing & forwarding, transportation, supply, receipt and unloading at site, storage, insurance at all stages, associated civil works, electrical works, services, permits, licenses, operational acceptance testing, commissioning, performance demonstration of Mono-Crystalline PV technology 100MWAC Capacity Grid Interactive Solar PV Power Plant with the highest proven Mono Crystalline PV technology at Village Jiwachiwadi, Taluka: Kaij, District: Beed, Maharashtra.
The solar power generated from above project shall be evacuated at the Delivery Point i.e. MSETCL/ MSEDCL Sub-Station including 3 years Operation & Maintenance of 100MWAC Solar Power Plant after successful commissioning of the project.
Powered by Capital Market - Live News